Al Zahira Substation
Damascus, Syria
Company Participation: Sub-Contractor to Ansaldo Co.
Client: P.E.E
About Project
The project includes:
- 230 KV section: /3/ power transformers, capacity of each is: 125 MVA. /3/ line bays.
- 66 KV Section: /3/ incoming bays. /6/ line bays.
Significance of the project:
- Improving reliability of the network at south and north of the city.
- To reduce loads on the existing substations in the city.
- Improving voltage status in Damascus city.
FTCC was involved in all the civil and erection works of the project.